On early of March 2018, BICP had to mobilize the heavy equipment using LCT to the IUP OP PT Harindo Wahana’s site which is located at Tering District, Kutai Barat Regency, East Kalimantan Province.
Followed with land clearing work and developing mine infrastructures.
Exploration activities are carried out by drilling using a jacro – 175 drilling machine. The average drilling depth is up to 50 meters.
Up to now 45 holes has been drilled with a total depths of ± 2.250 meter.
From the results of the exploration that has been carried out, it is set to do mining in two blocks :
– East Block ± 15 Ha
– West Block ± 35 Ha
Measured reserves of the two blocks are ± 3,000,000 MT which is targeted to be mined within 3 years.
Mining activities are carried out with strict supervision by placing work safety as a top priority.
The quality and professionalism of selected human resources are expected to be a strong foundation to achieve the target of quantity and quality that has been set to meet customer needs and satisfaction.
Years Established
Completed Projects
About Borneo Indocoal
PT Borneo Indocoal Perkasa (BIC) was signing the joint operation agreement number 045/HW-BIP/II/2018 with PT Harindo Wahana on February 15th, 2018. Based on this agreement BIC has the legal right to do mining operation, transportation and coal selling for the coal produced from IUP-OP PT Harindo Wahana SK Bupati Kutai Barat Nomor 545/K.875.a/2010.